EB 58
Jamestown Boat Yard replaced the turbochargers and intercoolers of the Grand Banks Eastbay 58 with upgraded models, raw-water impellers, batteries, breaker panels, tank monitors and on and on (read more and view the photo gallery).
At right: extreme heat destroyed the electronics suite at the helm.
Here is a partial list of replacement parts:
Breaker panel: two AC and two DC panels were replace as per original; new DC wiring from breaker panels to new terminal strips mounted behind hinged panel door; wires leading to terminal strips from throughout boat were reconnected using new ferrels.
Genset control: two new
Tank Sentry Monitor: two new
Helm panels: salon and bridge panels were newly fabricated by Common Gound Inc.
Salon helm terminal wiring: new wiring from panel to new terminal strips; new wires leading to terminal strips from salon terminal strip; new wires connecting bridge and salon terminal stips
Bridge helm terminal wiring: new wiring from panel to new terminal strips; wires leading to terminal strips from throughout boat were reconnected using new ferrels.
Caterpillar color MPD: four new
Caterpillar Multi-Station Control: one new
Caterpillar Keyswitch/alarm panel: four new
Caterpillar cable and cable tees: new / reused as needed
Wiper motors: three new including new wiring and water plumbing
Interior light fixtures: replaced all throughout
Interior light fixture switches: replaced all throughout
Interior light wiring: replaced all throughout
Interior electrical outlets: replaced all throughout including GFI
Trim tab control: one new
SeaFire: two new controls and new main system
Nav instruments: new
Bow thruster control: two new controls
Spot light: new Power Control Module, including complete new cabling
Clothes washer: new including new wiring
Clothes dryer: new
Dish washer: new
Oven: replace control panel
Microwave: new
Service Batteries: four new, high end 8D AGM
Engines
After coolers: two new, upgrade version
Turbochargers: four new
Raw water impellers: new
Strainers: cleaned
Belts: new
Zincs: new
Milton Cat: Bob Peckam of Milton Cat performed start-up commissioning and installation of aftercoolers
Start Batteries: two new, high end 8D AGM
Generators
Belts: new
Raw water impellers: new
Strainers: cleaned
Zincs: new
Start Batteries: two new, high end 4D AGM
Bottom
Strip to gelcoat: soda blast
Barrier: Interprotect 2000
Bottom paint: signal coat plus two coats sprayed
Scoops: clean
Zincs: new
Props
Balanced: Accutech job#s C100089 & C100088
Correct pitch: Accutech job#s C100089 & C100088
Polished: Accutech job#s C100089 & C100088